New Year’s Shrine Update!

After a short break for the holidays work, continues at the Shrine. Shop drawings of the roof truss steel were received and are being reviewed by Wiss, Janney, Elstner Associates, Inc. Once reviewed and approved, the steel can start fabrication. Fabrication will take 6 to 8 weeks – just in time to erect steel when the spring starts to thaw!

The cold temperatures of winter have put a hold on the tower repairs. The parapet has been protected for the winter.